How to define Resource Productivity in Primavera P6 and create schedule

When create a schedule, we can based on Resource Productivity to estimate duration. For example: We have a team which can cast 10 m3 of concrete per day (This is Productivity) We have an Foundation which take 100 m3 concrete. Duration of Foundation activity will be  100 / 10 = 10 days Now we will do it... Continue Reading →

Advertisements

How does Resource Shift Calendar in Primavera P6 work?

In Primavera P6 -> Resources window -> Units & Prices tab, there is a selection box called Shift Calendar What does it use for? I'll show how to use it in this article. The Shift Calendar control the Price/Unit for activity, depend on what time activity start and finish. For example, we have resource B which... Continue Reading →