How to define Resource Productivity in Primavera P6 and create schedule

When create a schedule, we can based on Resource Productivity to estimate duration.

For example:

  • We have a team which can cast 10 m3 of concrete per day (This is Productivity)
  • We have an Foundation which take 100 m3 concrete.
  • Duration of Foundation activity will be  100 / 10 = 10 days

Now we will do it in Primavera.

Supposed that we have a schedule like below picture:

How to define Productivity in Primavera P6 and create schedule-1

First we need to change Duration type of all activity to “Fixed Units/Time” Continue reading “How to define Resource Productivity in Primavera P6 and create schedule”

Advertisements