How Early and Late date are calculated in Start to Start relationship in Primavera P6

In Finish to Start relationship, Primavera calculate Early and Late date base on 2 process Forward Pass (to calculate Early Start and Early Finish) Backward Pass (to calculate Late Start and Late Finish) In Backward Pass, the Late Start of successor (Activity C) will be the base to calculate Late Finish of predecessor (Activity A... Continue Reading →

Advertisements

Filter activity by Relationship Type in Primavera P6

Sometimes we need to filter activities based on relationship type. For example we want to show only activity which has Finish to Start relationship. However the default filter function doesn't support it. I will show you how to do it. We will use Report function in this case. We have a simple project and we will... Continue Reading →