Automatically update progress in Primavera: The difference between Apply Actuals and Update Progress

In Primavera, when you need to make a quick update of project (Let's say everything goes as it's planned) we have 2 ways of automatically update progress: Apply Actuals Update Progress Here I will only explain what is the difference between these 2 options. The Apply Actuals function will update any activities with the "Auto Compute Actuals"... Continue Reading →

Advertisements

Turn off Auto Compute Actuals for 1 activity

By default our project check this option like below image so that when you update Duration % complete, P6 will update Actual units for you. When you don't want this happen, you can turn it off. However it will apply to the whole project. How about you want to turn it off for only one... Continue Reading →