How to define Resource Productivity in Primavera P6 and create schedule

When create a schedule, we can based on Resource Productivity to estimate duration.

For example:

  • We have a team which can cast 10 m3 of concrete per day (This is Productivity)
  • We have an Foundation which take 100 m3 concrete.
  • Duration of Foundation activity will be  100 / 10 = 10 days

Now we will do it in Primavera.

Supposed that we have a schedule like below picture:

How to define Productivity in Primavera P6 and create schedule-1

First we need to change Duration type of all activity to “Fixed Units/Time” Continue reading “How to define Resource Productivity in Primavera P6 and create schedule”

Advertisements

How Early and Late date are calculated in Start to Start relationship in Primavera P6

In Finish to Start relationship, Primavera calculate Early and Late date base on 2 process

  • Forward Pass (to calculate Early Start and Early Finish)

how-early-and-late-date-are-calculated-in-start-to-start-relationship-in-primavera-p6-1

  • Backward Pass (to calculate Late Start and Late Finish)

Continue reading “How Early and Late date are calculated in Start to Start relationship in Primavera P6”

Change Hours/Day in Calendar but keep Activity Duration unchanged in Primavera P6

We make a schedule using 8 hours/day calendar.

change-hours-day-in-calendar-but-keep-activity-duration-unchanged-in-primavera-p6-1

Now we want to change to 10 hours/day calendar.

change-hours-day-in-calendar-but-keep-activity-duration-unchanged-in-primavera-p6-2

We can see the Activity Duration now change to 8 days and Project Completion date is now earlier.

How can we change Hours/day but keep duration unchanged?

I will show you how to do it. Continue reading “Change Hours/Day in Calendar but keep Activity Duration unchanged in Primavera P6”

How to update Baseline in Primavera P6

Baseline is something we usually do not change. However in some case we need to change it.

I will show you how to do it.

We have a simple project which is assigned a baseline

How to update Baseline in Primavera P6 - 1

After a few update period, the project is delayed quite far from the baseline Continue reading “How to update Baseline in Primavera P6”

How to display just One Critical path with Multiple projects open in Primavera P6

In Primavera we can work with multiple projects at the same time.

We have a Program contain 2 projects : Project 1 and Project 2.

How to Display just one Critical path with Multiple projects open - 1

Each project has its own critical path. And when we open 2 projects, by default Primavera show 2 critical paths.

What if we want to show only 1 critical path for the program.

I will show you how to do it. Continue reading “How to display just One Critical path with Multiple projects open in Primavera P6”