What does The Carat (^) Symbol next to the Resource Price/Unit in Primavera P6 mean?

When we assign resource to activity, sometime we can see a carat (^) symbol appear in Price/Unit column. The carat (^) is displayed when the resource does not have a price/unit assigned. If resource does not have price/unit, Primavera will use the Project level price/unit which is defined in Project window -> Calculation tab Now... Continue Reading →

Advertisements

When do we use “Store Period Performance” function?

In my project, I receive updated data from construction team every month. However, they never update data correctly in that period. For example, this month is December, most of activity they update start and finish within December but there are always some activities which is updated in November or even in October. (They said they... Continue Reading →