How does Primavera P6 summarize data in the Summary / Grouping Band

We may wonder How does P6 calculates and displays summary information for costs, quantities, user defined fields, dates, durations, float, progress... I will explain it in this article. These calculations and display summaries are based on the currently visible activities. Activities removed from the layout by filters are not included in the calculations and summaries.... Continue Reading →

Advertisements

How to define Resource Productivity in Primavera P6 and create schedule

When create a schedule, we can based on Resource Productivity to estimate duration. For example: We have a team which can cast 10 m3 of concrete per day (This is Productivity) We have an Foundation which take 100 m3 concrete. Duration of Foundation activity will be  100 / 10 = 10 days Now we will do it... Continue Reading →