How to perform Impacted As-Planned Delay Analysis in Primavera P6

The Impacted As-Planned method measures the impact of the delays on the as-planned schedule. The delays are formulated as activities and added to the as-planned schedule showing the effect of each delay and demonstrating how the project is being delayed. The amount of delay equals the difference in completion dates between the schedules before and after the impacts.

We have an As-Planned schedule.

how-to-perform-impacted-as-planned-delay-analysis-in-primavera-p6-1

We will insert Delay event into our schedule. Continue reading “How to perform Impacted As-Planned Delay Analysis in Primavera P6”

Advertisements

How to perform Time Impact Analysis / Window Analysis in Primavera P6

A Time Impact Analysis is a method used to determine extent of impact from potential delay in construction process. This schedule analysis method involves the insertion or addition of activities indicating delays or changes into an updated schedule representing progress up to the point when a delay event occurred to determine the impact of those delay activities.

Types of Delays

Delays can be categorized in two main areas:

  1. Excusable Delays

Excusable Delays occurs due to events which are outside the control of contractor like heavy rains, storms, strikes, fire, client suggested changes, differing site conditions, change of government policy… etc.

When there are excusable delays, contractor is entitled to time extension in case date of completion is extended. Such delays can also affect non critical activities which must be considered with more detailed analysis.

Excusable delays can be further classified in compensable and noncompensable delays.

  • Excusable Compensable Delays
    As name suggests excusable compensable delays are those in which contractor is entitled for extra payment (compensation) i.e. monetary compensation and time extension as well. But decision that a delay is compensable or noncompensable is taken as per contract between client and contractor. Natural disasters or some reasons which are out of control are not considered. Example of such delay could be that client doesn’t allow access to site even after notice to proceed is given; other such delays which are due to client are compensable.
  • Excusable Noncompensable Delays
    Such delays are such where both contractor and client are not responsible for delay. Under such circumstances only time extensions are granted and no monetary compensation is provided. Such delays include act of God.

2. Non-Excusable Delays

As name suggests these delays are such that they don’t have any excuse or no excuse can be given for them. They arise due to carelessness or actions and inactions of contractors and subcontractors. For such delays no time extensions and monetary compensation is given to contractor if it has affected whole duration of project. In such cases client is liable to get liquidated damages. Example of such delay could be constructing something wrong which is not given in drawings, not completing work on time, improper resource allocation etc.

We have a simple project with the Planned schedule like this:

How to perform Time Impact Analysis Window Analysis in Primavera P6 - 2

1st month.

We have delay (21 days) on Excavation due to Unforseen site condition Continue reading “How to perform Time Impact Analysis / Window Analysis in Primavera P6”