How to highlight a Time period in Gantt chart in Microsoft Project

MS Project do not provide a tool to highlight a time period in Gantt chart. So how can we do it? First you create a new calendar. For example "Gantt Shade" In Exception tab, add the Time period you want to highlight. (From January to March) Right click on Gantt chart and select Nonworking Time...... Continue Reading →

Advertisements

How to edit Project calendar in Microsoft Project

By default when we create a new project in Microsoft Project it use 5 day work week. How about we want to use 6 day work week. I will show you how to do it. We have a simple project using default 5 days work week. We can see a task with 10 days duration start... Continue Reading →