What does The Carat (^) Symbol next to the Resource Price/Unit in Primavera P6 mean?

When we assign resource to activity, sometime we can see a carat (^) symbol appear in Price/Unit column.

1

The carat (^) is displayed when the resource does not have a price/unit assigned.

7

If resource does not have price/unit, Primavera will use the Project level price/unit which is defined in Project window -> Calculation tab

2

Now if you define price/unit for the resource like this:

3

Primavera will now use the price/unit from resource.

However you have to run “Tool -> Recalculate Assignment Costs” to refresh the data.

4

Click on Recalculate

5

Now you can see there is no carat (^) symbol in the price/unit and that price is taken from Resource.

6

Advertisements

Author: doduykhuong

Chief Planning Engineer. Scheduler. Oracle Primavera P6 Certified Specialist. Provide Primavera P6, Microsoft Project Tips & Tricks

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s