Print report show predecessors in Gantt chart

To show Predecessors of an activity we can use Relationship tab:

1

However it’s quite difficult to identify what are those activity.

How about we can show them in Gantt chart. That will be more easy to understand.

First you choose View -> Collapse All.

Go to the activity you want to show Predecessors. Select a Predecessors and click the GoTo button.

2

When you click it, you will jump to that Predecessor, and the WBS of that predecessor will expand.

You will do one by one predecessor.

To hide all other unnecessary bar, you can read this article : https://doduykhuong.wordpress.com/2016/02/19/make-report-to-show-only-some-wbs-in-gantt-chart/

Now you will have a report which show all predecessors in Gantt chart:

3

3

Advertisements

Author: Khuong Do

Khuong Do is a Project Planner in Civil, Transportation and Oil & Gas Industry. He has worked as a Primavera Consultant Specialist since 2006 . He holds a Civil Engineering degree and a Bachelor of Information Management System. Now he is working in Petronas RAPID project, one of the biggest Refinery and Petrochemical complex, in Pengerang – Malaysia.

Leave a Reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s